HOME EXTENSION REPAYMENT SCHEDULES − METHOD A VS. METHOD B

There are two options available when it comes to payment schedules: Method A and Method B. Over the last few years, as banking institutions have become increasingly hypersensitive and over-reactive, there has been some deliberation to extension builders using Method B as the basis of their payment schedule.

What is Method A?

The Master Builders Home Improvement Contract contains two methods of progress payment schedules. Method A is used generally for new home builds as the payment schedules reflect the standard stages of construction.

Table of payments and progress payments Method A:

Type of contract % of Contract Price Amount $ Payments and stages
Contract to build all stages 5% Deposit
10% Base stage
15% Frame stage
35% Lock-up stage
25% Fixing stage
10% Final payment
100% Total

The above schedule is very rigid and inflexible perfectly suited to a new home build.

What is Method B?

For an extension / renovation Method B allows the builder and the client the flexibility to stay in their home as extension works are progressing, thus avoiding potential costs of moving out and having to rent a property for the duration of the build.

Method B Img 1024x639 1

This method is determined on a job-by-job basis to achieve the fairest and best balance of amenity for both the Client and the Builder.

To demonstrate this, imagine a second storey extension being erected whilst retaining use of your ground floor amenities. Ground floor works will then proceed with installation of the stairs allowing access to the upper level for work required to be carried out by the Client. The Project Manager will discuss timing and progression of works prior to site start at the Pre-commencement meeting.

Why is Method B best for Extensions & Renovations?

Let’s compare. Method A lists ‘Frame Stage’ as a fixed option. For a second storey extension that would require ALL of the framework to both the upper and lower floors to be completed at the same time. How does a family live through this from a practical point of view? Remember, our aim is to keep you in your home with minimal disruption whilst we complete your extension.

By using Method B, we are able to bring the second storey extension to ‘Lock-up stage’ before beginning downstairs work. This is only one example of many as each payment schedule is specific to the Project.

Testimonials

Other Information posts

94 Deakin St High Res 3

LOCAL HOME EXTENSION BUILDERS

Seeking a local home extension builder is often part of an initial strategy for finding a home extension builder. Local extension builders should not however require to have a head office in…
Read more
Permitneeded

DO I NEED A PERMIT FOR THIS?

If you are considering building, renovating or simply undertaking some work on the property then you must first ask yourself: “Do I need a building permit for this?” The Building…